The Project Management Processes :
to continue our study of project management and know the phases of the project which through .
now we should know the Project Life cycle types :
Predictive :
project scope , time and cost are determine in the early project phases .(Waterfall)
Iterative :
Project scope is generally determined early , time and cost estimated .(research document like corona virus ).
Incremental :
the deliverable is produced through a series of iterations , and each iteration adds functionality to the deliverable .
Adaptive :
iterative and incremental called change driven (IOS-Android ).
Project Management Processes :
the project life cycle is managed by executing a series of project management activities
so we can say every project management process produce one or more deliverables or output from one or more input using tools and techniques , project management process linked by outcomes /deliverables , an output may be an input to other process or deliverables .
Process Group :
Logical grouping of project management processes to achieve specific project objectives .
Initiating :
to define new project / phase by obtaining authorization .[2 process]
Planning :
establish scope - define objectives and cause of action to achieve them .[24 process]
Executing :
to complete the work defined in the project management plan to satisfy requirements .[10 process]
Monitoring and control :
to track and review the progress and performance and to initiate the required changes .[12 process]which there actual states and planned statues and do (root cause analysis ) to compare between them to see if there any variance between them do correction action to solve past actions and preventive action to prevent any problem or action in the future .
closing :
to formally complete a project phase or contract . [1 process]
to be totally 49 processes .
Project management Data & Information :
Work Performance data : in Executing process
Row observation - row measurements - start /finish data -actual cost/duration .
so it's consider the actual data occurred in the executing process like the sand truck be in site at 8 am and finish at 1pm so put 5 ton sand with the total cost 100 $ so like that .
Work performance information : in controlling process
Compare the actual data to the planned data to get information , and know if any variance the the change status , so need to collect the performing data and know the deliverable status if completed or validated to the end user .
Work performance Report : overall control
it's consider physical or electronic presentation of W.P.I.
like dashboards - updates - recommendations .
the meaning of ITTOS :
Input Techniques Tools and Output .
The Tailoring management processes :
the selection of appropriate project management processes ,ITTOS and life cycle phases .
Project management Documents :
The Project sponsor is accountable for development of business .
The Project manger is responsible to keep the project objectives .Business Case :
a documented economic feasibility study used to ensure validity of the benefits of selected component to obtain authorization for further project management activities .Business needs : business problem -scope - value .
Situation needs : strategies - risks-success factors .
Recommendations : How - when - who of resources .
Benefits management plan :
a documented explanation defining the processes for creating and maximizing and sustaining the benefits .
Target benefits : net -value - time frame
Owner benefits
Strategic alignment like Egypt 2030 .
Metrics .
Project charter :
a documented issued by project sponsor which provide the project manager authorization to apply resources to project activities .
- Initial scope .
- initial budget
- initial schedule .
- main stakeholders .
- sponsor approval .
Project management plan :
document that describes , how the project will be executing , monitoring and control and closed , have 12 subsidiary plan (scope-cost-schedule ,.....etc)
3 Baselines (Scope-Schedule - Cost ) .
0 Comments